Below are just a few of the many things going on behind the scenes with our building project.

 

TAKE 4:  MAY-JUNE 2020

Below are some of the key target dates and activities we are working toward during the latter part of May through the end of June:

  • May 21 – GC selected – Batson-Cook Construction
  • May 29 – GC pre-construction engagement commences
  • June 01 – 80% plan set ready for initial building permit application
  • June 05 – Waters systems and curb staking scheduled for completion
  • June 26 – Site electrical conduits and irrigation sleeving scheduled for completion
  • June 30 – Curb and gutter under way