Work is continuing on pre-slab preperation. Gravel was spread over the slab area and initial slab pouring is scheduled for this week (weather permitting). Below is a summary of last week’s progress:

  • Installed under slab electrical to the electrical room.
  • Roughed in restrooms.
  • Poured elevator pit walls.
  • Installing domestic water line.